Duplex Stormwater System Upgrade for a New England University

Gustavo Preston replaced a long-serving university duplex sump pump system with a new Weil duplex submersible stormwater system. The upgrade restored full pumping capacity and backup protection after one of the original pumps failed, and the installation was smooth and was well planned.

The university’s facilities team contacted Gustavo Preston to replace a very old HOMA duplex submersible sump pump system. The system was originally designed with two pumps, but one had failed, leaving a single aging pump to handle the full load. After years of service, the equipment was due for replacement, and the team wanted a dependable, long-term fix.

On a campus, a stormwater pit that fails during heavy rain can flood mechanical spaces and disrupt buildings in use. With only one pump still running, the university had no backup if that pump stopped working.

Rather than replacing only the failed pump, Gustavo Preston recommended a complete system replacement:

  • Weil duplex submersible stormwater system. Two new pumps restore the system’s original design capacity and redundancy. The pumps share the load, and if one fails or demand peaks during a heavy storm, the other is ready to run.
  • New check valves. These replace the original valves, which had aged along with the pumps. New valves prevent backflow into the pit and protect the new pumps.
  • New discharge piping. The existing piping was old and due for replacement, so it was replaced along with the check valves, leaving the system in better condition and easier to service.

This approach addressed the whole system, not only the part that had failed.

Prior to installation day, the lead technician inspected the site to confirm conditions and lay out a plan for installing the new system. The walk-down covered the pit, the existing piping and valves, access routes, and how the new pumps and discharge piping would fit.

With that preparation done, the crew arrived knowing the scope, sequence, and materials needed. The installation went smoothly and efficiently, with minimal disruption to campus operations.

The university now has a fully functioning duplex stormwater system with redundancy restored, along with new check valves and new piping. The university’s Facility Engineer was very pleased with the installation.

  • Full pumping capacity restored, with both pumps back in service
  • A backup pump ready to run if one pump fails or during heavy storms
  • New check valves and piping that make the system more reliable and easier to service
  • A well-planned, efficient installation that kept disruption low

Gustavo Preston continues to support the university as a long-standing customer.

Contact Us

Choose Gustavo for high-quality, comprehensive service and solutions.